Back for phase 3 at the CTS Amiri project on Portsdown Hill. With the steel frame now in place Amiri are now moving forward with their superstructure work whilst HWM Group have started to lay the concrete for the service yards and roadways around the building.
Pumped concrete is providing a 175mm slab being poured in two sections which will create a safe zone for storage of materials for the remainder of the build as a working platform.
Our team will then move in to the building to start the ground floor slab, insulation and below slab drainage returning later in the year to continue with outside works.